掀开奶罩边躁狠狠躁苏玥视频,无码专区3d动漫精品,去阳台跪着把屁股抬起来,精品国产丝袜黑色高跟鞋


Ivanhoe’s modest gains reflect progress at Kakula

  • Tuesday, August 11, 2020
  • Source:ferro-alloys.com

  • Keywords:Ivanhoe,DRC,Kakula
[Fellow]Ivanhoe’s modest gains reflect progress at Kakula

[ferro-alloys.com]Canada’s Ivanhoe Mines (TSX: IVN) reported on Monday a drop of over 90% in income during the second quarter of the year from the same period in 2019 as its moves forward with its flagship copper project in the Democratic Republic of Congo, which will see first production earlier than planned.

The Vancouver-based miner recorded a total comprehensive income of $0.3 million for the three months to June 30, compared to $8.1 million in the second quarter last year.

Finance income, however, amounted to $18.7 million, compared to $16.9 million last year, partly thanks to the interest earned on loans to the Kamoa Holding joint venture to fund progress in the DRC. 

Development of the Kakula copper mine, the first of multiple planned mining areas at the massive Kamoa-Kakula project, continues to exceed expectations.

Ivanhoe said more than 18.7 kilometres of underground work is now complete, which is 5.5 kilometres ahead of schedule. Crews recorded 1,635 metres in July alone, or 257 metres more than targeted for the month.

Ivanhoe also said the Kakula’s 2,000-tonne-per-hour ore conveyor system is undergoing final commissioning and will begin continuous operations “shortly.”

“Once this happens, the ore mined in the northern portion of the Kakula Mine will be combined and be placed on a blended surface stockpile,” Robert Friedland, the company’s co-chair, said. “The Kakula South and Kansoko declines are not equipped with conveyor systems; as such, the ore mined from these deposits will continue to be placed on separate surface stockpiles, based on copper grades.”

World’s highest-grade copper mine

Friedland, who made his fortune from the Voisey’s Bay nickel project in Canada in the 1990s, has been working on Kamoa-Kakula for ten years.

The mining billionaire believes the overall project, being developed in partnership with China’s Zijin Mining Group, will become the world’s second-largest copper mine.

The Kakula mine is expected to be the highest-grade major copper mine in the world, with production rate of 3.8 million tonnes per year initially.

At the end of July 2020, the project’s high-grade ore stockpile contained an estimated 116,000 tonnes grading 6.08% copper. Kakula and Kansoko’s medium-grade ore stockpiles contained a combined additional 446,000 tonnes at 2.73% copper.

It is also designed to have one of the top environmental footprints in the industry across tier-one copper operations, Friedland said.

“It will be powered by clean, renewable hydroelectricity and be among the world’s lowest greenhouse gas emitters per unit of copper produced. It also will have a relatively tiny surface footprint as approximately 55% of the mine’s tailings will be pumped back into underground workings,” he said.

Ivanhoe pegs Kakula’s initial capital cost at $1.3 billion (including pre-production ore stockpiles) and expects first concentrate production in the third quarter of 2021.

Kamoa-Kakula is a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the DRC government (20%).

The company also is exploring for new copper discoveries on its wholly-owned Western Foreland exploration licences, adjacent to the Kamoa-Kakula mining licence.

Ivanhoe is also advancing the Platreef palladium-platinum-nickel-copper-gold-rhodium discovery in South Africa; and the extensive upgrading of the historic Kipushi zinc-copper-silver-lead-germanium mine, also in the DRC.

(Mining.com)

  • [Editor:王可]

Tell Us What You Think

please login!   login   register
Please be logged in to comment!
主站蜘蛛池模板: 镶黄旗| 固阳县| 江油市| 沁水县| 平谷区| 石台县| 赤峰市| 临夏市| 垦利县| 信宜市| 奉贤区| 河曲县| 家居| 镇安县| 江城| 会理县| 眉山市| 句容市| 外汇| 美姑县| 随州市| 龙南县| 石嘴山市| 太康县| 多伦县| 霞浦县| 平武县| 察隅县| 高阳县| 建阳市| 许昌市| 哈密市| 额敏县| 饶河县| 石台县| 溧阳市| 阿鲁科尔沁旗| 凭祥市| 澄迈县| 东乡族自治县| 磐安县|