US construction slowed by difficulties to source electrical steel amid lack of investment

  • Tuesday, June 11, 2024
  • Source:ferro-alloys.com

  • Keywords:US construction, electrical steel
[Fellow]It was not possible to obtain a reply from Cleveland-Cliffs to requests for comment by the time of publication.

[Ferro-Alloys.com]

US construction contractors – including for residential, commercial and manufacturing facilities – have reported long delays and unpredictability in obtaining electrical transformers. This is due to inadequate electrical steel supplies amid missing investment decisions in the US to expand production of the material.
 
Contractors reported “extremely long and unpredictable lead times” for transformers, Kenneth Simonson, chief economist of the Associated General Contractors of America (AGC), told Fastmarkets on Monday April 15.
 
Contractors waiting for electrical transformers are “quoted a long lead time and then told of a further delay when the delivery date is imminent,” Simonson said.
 
“I’m not close to electrical equipment manufacturers or their steel suppliers but I’m told that Cleveland-Cliffs, the principal supplier of grain-oriented electrical steel that’s essential for transformers, has been reluctant to expand production, which is producing the long lead times,” he added.
 
It was not possible to obtain a reply from Cleveland-Cliffs to requests for comment by the time of publication.
 
Similarly, the Edison Electric Institute (EEI) – an association that represents US electric companies – said in a statement that “electric companies today still are facing unprecedented lead times for transformers.”
 
The AGC and the EEI – along with groups such as the National Association of Home Builders, the American Public Power Association and Leading Builders of America – wrote to the Senate and House in November 2022 to ask for $1 billion that year to address the problems with transformer supplies.
 
Material availability was identified as a leading cause in the delays. The letter included recommendations such as “building manufacturing capacity to support long-term demand and investing in domestic production of grain-oriented electrical steel (GOES), a key transformer component.”
 
Between 2020 and 2022, average lead times to produce transformers across all segments of the electric industry and voltage classes had increased by 443%, the letter said. Orders that previously took two to four months to fill were at the time “taking on average over a year.”
 
“Construction and electrification projects are now being deferred or canceled” while delays were making it harder to address housing affordability, the organizations added.
 
Demand for GOES electrical steel is set to expand greatly over the next decades at a faster pace.
 
According to the AGC’s most recently released statistics, total US construction spending rose by 11% in February compared with the same month a year earlier. Manufacturing construction gained the most, with a 32% increase.
 
Private residential construction expanded by 7%, while office construction expanded by 6%, the AGC added.
 
US Steel announced in October the start of a new electrical steel line in its Big River plant in Osceola, Arkansas, but it makes the non-grain oriented electrical steel (NGOES) that is used in making electrical motors of electric vehicles and hybrids. fastmarkets
  • [Editor:kangmingfei]

Tell Us What You Think

please login!   login   register
Please be logged in to comment!
主站蜘蛛池模板: 苏尼特左旗| 北票市| 阜南县| 昌宁县| 志丹县| 宣化县| 宁晋县| 临澧县| 天柱县| 长子县| 龙海市| 阿鲁科尔沁旗| 琼结县| 兴化市| 珠海市| 许昌市| 南开区| 疏附县| 同德县| 吴堡县| 独山县| 平南县| 娱乐| 澎湖县| 柳江县| 皮山县| 浦北县| 临高县| 宣城市| 扶风县| 万安县| 铁岭县| 扬州市| 大荔县| 霍州市| 收藏| 常熟市| 双鸭山市| 和龙市| 玛多县| 英超|